Binton Bridge : Revised Works Schedule

Traffic Management Programme Traffic management 236 days Mon 02/10/23 Fri 24/05/24 Type Road closure (with pedestrian access) 12 days Mon 02/10/23 Fri 13/10/23 2-way temporary lights 23 days Sat 14/10/23 Sun 05/11/23 Road closure (with pedestrian access) 47 days Mon 06/11/23 Fri 22/12/23 Fully open (Christmas break) 30 days Sat 23/12/23 Sun 21/01/24 Road closure (with pedestrian…

Digital Switchover Update

The UK’s telephone network is changing. By the end of 2025, most telephone providers will have moved their customers from landlines served by the old analogue (copper) network to new upgraded landline services which use digital technology. This is commonly referred to as The Digital Switchover. BT Consumer Group – the largest provider of landline…