Binton Bridge : Revised Works Schedule

Traffic Management Programme

Traffic management 236 days Mon 02/10/23 Fri 24/05/24
Type
Road closure (with pedestrian access) 12 days Mon 02/10/23 Fri 13/10/23
2-way temporary lights 23 days Sat 14/10/23 Sun 05/11/23
Road closure (with pedestrian access) 47 days Mon 06/11/23 Fri 22/12/23
Fully open (Christmas break) 30 days Sat 23/12/23 Sun 21/01/24
Road closure (with pedestrian access) 47 days Mon 22/01/24 Fri 08/03/24
2-way temporary lights 37 days Sat 09/03/24 Sun 14/04/24
Road closure (with pedestrian access) 12 days Mon 15/04/24 Fri 26/04/24
2-way temporary lights 28 days Sat 27/04/24 Fri 24/05/24
Fully open Fri 24/05/24

Please note these times and durations are subject to review as the works are progressed.